Connect with us

Business

Electricity transmission restored across country: Power Division

Published

on

  • An accidental fault had triggered an almost day-long power outage in the Southern parts of Pakistan.
  • The fault could not be fixed despite passing of more than 24 hours since it was detected.  
  • Power Division says only routine power load-shedding is being carried out in country.

LAHORE/ISLAMABAD: After an almost day-long outage, the Power Division on Friday said that electricity transmission and generation have been restored across the country adding that only routine power load-shedding is being carried.

“Electricity transmission and generation have been restored across Pakistan including restoration of full supply from national grid to Karachi,” the division said in a statement.

Power outage yet to be controlled

Earlier today, sources within the National Transmission and Despatch Company (NTDC) had said that the countrywide power crisis, caused due to an “accidental fault” in the national grid, had not been controlled yet. 

Sources in the NTDC said that it was a major breakdown and could not be controlled even after 24 hours as the authorities have yet to identify the fault.  

The sources added that cities have been facing four hours of loadshedding while rural areas are suffering from a 12-hour-long power outage.

Meanwhile, power plants have not been fully energised and the country still faces a 4,500MW power shortfall while the frequency fluctuation is making things more complex.

The electricity is being restored from the power plants slowly to the system, said the sources. They added that this is the 16th breakdown in the last 10 years. 

Large parts of the country were in dark for more than 12 hours on Thursday after a fault was detected in the national grid’s southern transmission system.

Energy Minister Khurram Dastagir said that an “accidental fault” triggered the breakdown and announced the establishment of a committee to probe the matter and submit a report within four days.

‘Power supply will improve’

Meanwhile, the Islamabad Electric Supply Company (IESCO) spokesperson said that the electricity demand in the region is 1,280MW while the national grid is supplying 1,080MW.

Once the electricity supply is back to normal, the situation will improve, said the spokesperson. 

‘Power supply stabilised in Karachi’

In a statement, K-Electric said that the supply of electricity in Karachi was restored in a phase-wise manner. 

KE began phase-wise restoration efforts with first priority on strategic installations such as KWSB pumping stations, airports, and hospitals, said the power utility. 

Later, the supply was diverted to residential areas including but not limited to PECHS, Orangi, Lyari, Ibrahim Hyderi, Nazimabad, and Defence Housing Authority.

The technical constraints at the national grid may persist over the next 48 hours and to manage the constraints, KE may temporarily curtail power supply to industrial zones during nighttime hours to facilitate residential areas.

The power supply company said it may also have to conduct loadshedding.

Business

Exchange achieves all-time high: KSE-100 index surpasses 72,500 points

Published

on

By

With the benchmark KSE-100 index hitting a record-breaking high of 72,501 points, the Karachi Stock Exchange saw yet another incredible rise.

Within Pakistan’s financial environment, investors demonstrated a strong sense of trust in the market as the bullish trend continued.

As a result of the significant inflow of investment and optimism among market players, the index had an amazing 450-point rise during the trading session.

In their analysis of the market’s remarkable performance, financial analysts pointed to a number of causes for the upward trend, such as encouraging economic data, robust company profits, and the government’s proactive measures to promote economic expansion.

The durability and upward momentum of the market have also been greatly aided by continuous infrastructural investments and efforts meant to boost investor confidence.

In the meantime, interbank rates increased by six paisas, and the US dollar’s value saw a slight rise in the currency market. As a result of the current market conditions and the dynamic nature of foreign exchange swings, the dollar was quoted at Rs 278.45 in the interbank market.

Continue Reading

Business

The investment plan for K-Electric will be audited every three months.

Published

on

By

In light of K-Electric’s inability to persuade NEPRA with its Rs. 484 billion investment plan, the regulatory body has decided to hold off on making changes to the utility’s Transmission & Distribution Investment Plan until FY 2030.

As stated in the order, the NEPRA will select the terms of reference (ToR) for the third-party audit in addition to announcing the quarterly audit. A report on the company’s investment plan’s progress will need to be submitted every quarter.

A performance report would also be required under the investment plan by K-Electric, Karachi’s only power distribution utility, according to the statement. A secure mechanism to avoid electrical mishaps was also mandated by the authority to the utility.

In the meantime, the power distribution firm stated in a statement that the investment plan will boost the utility’s infrastructure to meet present and future demands, decrease transmission and distribution losses, and increase customer base growth.

With investments totaling Rs. 544 billion, KE has been able to more than halve its T&D losses and quadruple its customer base and power consumption since privatisation, according to the statement.

A hearing in March 2023 was held to inform stakeholders about the projects that KE management had planned for FY2024–FY2030, and the statement claimed that the plan had been presented in compliance with regulatory requirements.

In terms of investment areas including expansion, energy loss reduction, network rehabilitation, maintenance, and safety, KE claimed to have clearly defined priorities and projects for this era.

The plan calls for the construction of transmission lines and grids, which will increase the dependability of KE’s network and make it possible to take on more electricity from the National Grid.

In order to manage the city’s needs through targeted investments and tech-based interventions, CEO KE Moonis Alvi said, “We are looking to invest $2 billion in Transmission and Distribution over the next 7 years.” The work of all the stakeholders who have contributed to this trip and who will help us modernise our infrastructure and get ready for the future is something I’d like to acknowledge.

The investment plan is a supplement to the business’s Power Acquisition Programme, which outlines KE’s goal of having 30% renewable energy in its generation mix by 2030. As part of its efforts to provide everyone with access to reasonably priced energy, the firm has also been granted regulatory permission for its RFPs for 640 MW of renewable projects.

Continue Reading

Business

$399 million in airline revenue is being blocked by Pakistan. IATA

Published

on

By

Pakistan and Bangladesh have been urged by the International Air Transport Association (IATA) to promptly release airline profits that are being withheld in violation of international agreements.

“Airlines are unable to repatriate over $720 million ($399 million in Pakistan and $323 million in Bangladesh) of revenues earned in these markets, resulting in a severe situation,” an IATA statement stated.

“Money-denominated expenses like lease agreements, spare parts, overflight fees, and fuel must be paid for in a timely manner by repatriating revenues to their home countries.”

Delaying repatriation raises exchange rate risks for airlines and violates bilateral agreements’ international commitments. In order for airlines to effectively continue to offer the aviation connectivity that both of these countries depend on, Pakistan and Bangladesh must immediately release the more than $720 million that they are blocking, according to Philip Goh, Regional Vice President for Asia-Pacific at IATA.

Pakistan needs to make the difficult repatriation procedure less complicated. According to the statement, this presently includes the need to present audit certifications and tax exemption certificates, both of which create needless delays.

Approximately 425,000 jobs and $2.8 billion in economic activity were supported by Pakistan’s aviation industry prior to COVID-19. Passenger numbers are predicted to increase by more than 2.5 times by 2040 after returning to pre-COVID levels in 2023, according to the statement.

Continue Reading

Trending